Care Center Update – May 22, 2017

On the interior, the millwork continues.  The radius windows have been installed under the barrel roof and sheetrock is finishing around them.  Ceilings and lift systems continue to be installed along with lighting.

On the exterior, the walk under and drive under canopy structure are nearly complete.  Awnings are installed.