Care Center Update – June 19, 2017

The exterior site work is progressing, the sign base and stoops were poured last week. The walk under and drive under canopies structures are complete and ready for roofing and paint. The standing seam roofing on the barrel roofs has started and should be complete sometime this week.

The interior finishes are on the move with tile in bathrooms, wall finishes, ceilings, plumbing and lighting.