Monthly Archives: September 2016

Care Center Update – September 29, 2016

Structural steel erection started today with the beams and bar joist.


Care Center Update – September 26, 2016

Steel has arrived!!  A portion of the underground plumbing has been completed and will be completed after the steel framing is complete.   Currently storm sewer work continues on the south side of Vermillion Boulevard.    


Care Center Update – September 15, 2016

The foundation was finished on Monday, September 12.  Crews are starting on the underground plumbing because the joist and decking hasn’t been received yet.  


The Healthy Times – September 2016

Breast Cancer Awareness • Physical and Occupational Therapy • Woman’s Health Fair